STUDY OF RURAL ELECTRIFICATION PROJECT (CASE STUDY, IN LUEKU COMMUNITY KHANA LOCAL GOVERNMENT AREA) RIVERS STATE

Complete Material Cost #3,000

Order for Complete Material now

Abstract

Electricity is universally recognized as necessary, although not a sufficient, requirement for social and economic development. However, increasing access to electricity in developing counties has proven to be difficult and expensive, particularly in rural areas  Lueku  development by means of a cost benefit analysis of a typical rural  electrification project in Lueku community (Khana Local Government Rivers State), assessing the impact of electricity on households, education, agro-business, commerce and the public sector. We show that rural electrification can be commercially viable and cause structural transformation in rural areas within a short period of time. Finally, illustrated by the actual policy in Lueku is a key barrier to promote increased access to electricity for the poor.

 

TABLE OF CONTENT

 

Cover page……………………………………………………………………………………………………………………………………………i

Title page……………………………………………………………………………………………………………………………………………..ii

CERTIFICATION         iii

DEDICATION     iv

DECLARATION v

ACKNOWLEDGEMENT       vi

Abstract……………..    vii

TABLE OF CONTENT viii

CHAPTER ONE  1

INTRODUCTION         1

1.1     BACKGROUND OF THE STUDY  1

1.2     AIM OF PROJECT       2

1.3     SCOPE OF STUDY      2

1.4     SIGNIFICANCE OF STUDY 2

1.4.1  BENEFITS FROM RURAL ELECTRIFICATION       3

1.5     LIMITATIONS   3

CHAPTER TWO 4

LITERATURE REVIEW        4

2.1     THE GROWTH OF ELECTRICITY GENERATION,  TRANSMISSION, AND DISTRIBUTION IN NIGERIA         4

2.2     MATERALS USED IN RURAL ELECTRIFICATIONS        12

2.2.1  SUBSTATION DESIGN         12

2.2.2  FACTORS GUIDING THE LOCATION OF SUBSTATION 13

2.3     DISTRIBUTION LINE ACCESSORIES AND MATERIALS          14

3.3.1  POLE          14

2.3.2 CHOICE OF POLE        14

2.3.3  CHOICE OF OVERHEAD LINES   16

2.3.4  FACTORS TO BE CONSIDERED FOR OVERHEAD LINE            CONSTRUCTION          17

2.3.5  CHOICE OF CONDUCTORS          18

2.3.6  LOADING CONDITIONS OF OVERHEAD LINE POLE  STRUCTURES       19

2.4     WIND VELOCITY        19

2.5     LOADING CONDITIONS:     20

2.6       INSULATING MATERIALS         21

2.6.1  PROPERTIES OF GOOD INSULATION  21

2.7     TYPES OF INSULATORS     22

  • PIN TYPE INSULATORS 23
  • SHACKLE INSULATOR 23

2.8     DEFINITION OF TERMS      23

2.8.1  CONNECTED LOAD   23

2.8.2  MAXIMUM DEMAND 24

2.8.3  DEMAND FACTOR     24

2.8.4  AVERAGE LOAD        25

2.8.5  LOAD FACTOR  25

2.8.6  PLANT CAPACITY FACTOR        25

2.8.7  PLANT USE FACTOR 26

2.8.8  DIVERSITY FACTOR  26

2.9     LOAD         26

2.9.1  DOMESTIC LOAD       27

2.9.2  COMMERCIAL LOAD 27

2.9.3  INDUSTRIAL LOAD    27

2.9.4  MUNICIPAL LOAD      27

2.9.5  IRRIGATION LOAD    28

2.9.6  TRACTION LOAD       28

CHAPTER THREE       29

MATERIALS AND METHODS      29

3.1     COMPOSITION OF LUEKU COMMUNITY     29

3.2     THE MAP OF LUEKU COMMUNITY     29

3.3     LOAD ESTIMATION OF LUEKU COMMUNITY      29

3.3     OPTIONS OF SUPPLY ELECTRICITY IN RURAL AREAS        38

3.3.1  LOAD FORECASTING         39

3.3.2  LOAD SURVEY OF RURAL AREA       40

3.4     CURRENT INSTALLATIONS        43

3.5     DESIGN CONSIDERATIONS FOR SUBSTATION COMPONENTS     44

3.5.1 DISTRIBUTION TRANSFORMER 45

3.5.2  CHOOSING kVA RATING FOR THE LOAD    45

3.5.3  FEEDER PILLAR         45

3.5.4 CONDUCTORS AND CABLES      45

3.5.5  POLE          46

3.5.6  DESIGN CONSIDERATION OF LINE AND POWER TRANSFER;       46

3.5.7  AVAILABILITY OF SUITABLE AND SUFFICIENT LOAD;        47

3.6     MOUNTING OF TRANSFORMERS        49

3.6.1 PHYSICAL QUANTITIES OF CONDUCTOR   49

3.7     CHOICE OF MATERIALS FOR TRANSFORMERS  50

3.7.1  DETERMINATION OF CABLE FOR L.T AND H.T SIDES OF THE  TRANSFORMER          50

3.7.2 DETERMINATION OF VOLTAGE DROP ALONG THE LINE    51

3.8     PIN TYPE INSULATOR        52

3.9     SUBSTATION PROTECTION        52

3.10   SURGE DIVERTER     54

3.11   EARTHING         54

CHAPTER    FOUR      55

RESULT AND DISCUSSIONS        55

4.1     RESULTS 55

4.1.1  RESEARCH QUESTIONS    57

4.2     DISCUSSION      58

4.3     ELECTRICITY AND GROWTH    59

4.4     TESTING AND COMMISSIONING OF OVERHEAD  DISTRIBUTION  ON  LINES          63

4.4.1 GENERAL INSPECTION      63

4.4.2 TESTING    63

4.4.3  FACTOR TO BE CONSIDERED IN RURAL ELECTRIFICATION  DESIGN  64

  1. 5 CHOICE OF SYSTEM 65

4.6     CHOICE OF LOAD CENTRE         65

4.7     TYPES OF SUPPLY     65

4.8   LOAD DETERMINATION      66

4.9     LOAD FORECASTING          67

4.10   METHOD OF LOAD FORECASTING     67

CHAPTER FIVE 69

CONCLUSION AND RECOMMENDATION    69

5.1     CONCLUSION    69

5.2     RECOMMENDATIONS         70

REFERENCE      71

APPENDIX ONE 72

 

 

CHAPTER ONE

INTRODUCTION

1.1     BACKGROUND OF THE STUDY

Rural electrification is the supply of the rural areas, which is remote from the big cities. The rural areas is usually characterized by long distance village, setups and low power consumption demands which makes the financial investment in such rural electrification to be highly non-profitable with this attendance factor in mind, a suitable rural electrification design in terms of voltage level can only be achieved by understanding the total distance of the rural area to be electrified. Usually in practice, the two-feeder voltage levels normal employed in rural electrification are 11KV feeder voltage and 33KV feeder line. The rural electrification project usually considers the supply of electricity to a rural are through the shortest possible route and at affordable cost, most designs employ a rural system obtaining its supply from a nearby high voltage line. Using a distribution transformer and stepping the voltage from say 132kv to 33kv TO 11kv.

1.2     AIM OF PROJECT

The aim of this project is to contribute to economic and social development in Lueku through rural electrification. This will help in the development/higher growth of the community and reduce poverty. Also there will be increased agricultural production, processing and marketing facilities, there will be room from new industries and social amenities such as: hotels, cold stress etc.

1.3     SCOPE OF STUDY

Carrying out the local survey for a typical rural community, visits has to be made to the towns which are beneficial from the electricity  project, and on the spot assessment has to be made; we assume that Korokoro, Nyogor, Agbani, Wiikue, Baa, Kpaa, and Tem are in Lueku community.

1.4     SIGNIFICANCE OF STUDY

The provision of electricity in rural areas such  as Lueku   is widely believed to be a stimulus to increased agricultural productivity and output through irrigation and mechanization. to the growth of industries in the community and also to raise good living standards of rural people. Also, the benefits of rural electrification on Lueku community on social services delivery cannot be understated; immense contribution in the following sectors.

  1. Health delivery system
  2. I.C.T and communication it’s on economic development such as good irrigation, small to medium enterprise development.

1.4.1  BENEFITS FROM RURAL ELECTRIFICATION

Before examining benefits from rural electrification in detail, it is useful  to get an overall impression of how electricity consumption is.  For example, 90 percent of connected rural households in a surveyed area of the Lueku community where rural electrification is considered highly successful used less than 35 kilowatt-hours of electricity a month, about enough to use two 100-watt light bulbs for four hours a day.

Second, the weight of different sectors in total rural area electricity consumption varies enormously. 60 percent in residential-commercial share being quite high–about 25 to the surveyed areas of most communities   and consume most of the total in some rural areas.

1.5     LIMITATIONS

While carrying out this project, we encounter the few challenges. Locating the community was quite a task and also getting the map of the community. Due to the low mentality of some of the youth in terms of cultism, we were a bit tensed and less free to move around to get more materials / information’s.

Complete Material Cost #3,000

Order for Complete Material now